Heathfield Junior School

  • A total of 152 lights (10 different types) were replaced in 8 classrooms, 4 corridors and 3 toilets in the school.
  • A mobile scaffolding tower had to be erected to replace heavy, high level lighting in the school hall.
  • New emergency lighting was installed in every room.
  • All lights installed in the corridors are now controlled by a sensor with no switching required.
  • Three consumer units were upgraded complete with RCBO protection.
  • L&K carried out the lighting design.

 

 

Location: Twickenham

Client: London Borough of Richmond upon Thames

Would you like to discuss your current project with us?